Company or firm · first RERA registration 2019
Today Global Homes
Of 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 4 mo late — the same as Maharashtra's 4 mo.
Projects44 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record
3 registrations of 4 ran past the RERA date
Months late against the original RERA promise, per registration
4 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Anandam - Phase IP52000020292 | Panvel | Certificate Signed | 30 Dec 2024 | 30 Dec 2024 | On date |
| Anandam Phase - IIP52000021559 | Rohinjan | Certificate Signed | 30 Jun 2026 | 30 Oct 2026 | +4 mo |
| Anandam - IIP52000048037 | Rohinjan | Certificate Signed | 31 Dec 2027 | 30 Apr 2028 | +4 mo |
| Anandam IIIP52000077855 | Rohinjan | Certificate Signed | 31 Dec 2028 | 30 Apr 2029 | +4 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology