Company or firm · first RERA registration 2019

Today Global Homes

Of 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 4 mo late — the same as Maharashtra's 4 mo.

Projects44 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

3 registrations of 4 ran past the RERA date

Months late against the original RERA promise, per registration

4 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Anandam - Phase IP52000020292PanvelCertificate Signed30 Dec 202430 Dec 2024On date
Anandam Phase - IIP52000021559RohinjanCertificate Signed30 Jun 202630 Oct 2026+4 mo
Anandam - IIP52000048037RohinjanCertificate Signed31 Dec 202730 Apr 2028+4 mo
Anandam IIIP52000077855RohinjanCertificate Signed31 Dec 202830 Apr 2029+4 mo
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology