Skip to content
Company or firm · first RERA registration 2021

Tanish Properties

Deedo IDDD-FMQZ

Of 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 30 mo late.

Projects22 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay30 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

2 registrations of 2 ran past the RERA date

Months late against the original RERA promise, per registration

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Tanish Dreams BP52100029210WadmukhwadiCertificate Signed1 Apr 202430 Mar 2025+30 mo*
Tanish Dreams EP52100029235WadmukhwadiCertificate Signed1 Apr 202413 Feb 2025+30 mo*
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology