Of 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 4 mo late.

Projects77 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay4 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

3 registrations of 7 ran past the RERA date

Months late against the original RERA promise, per registration

7 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
PalomaP52100028735Adhale BkCertificate Signed28 Aug 202328 Aug 2023On date
Satvam Hills A5P52100052048JamgaonCertificate Signed24 Feb 202624 Feb 2026+8 mo*
Satvam Hills A4P52100052106JamgaonCertificate Signed31 Dec 202630 Jun 2025On date
Paloma - EvaP52100054156Adhale BkCertificate Signed31 Dec 202630 Apr 2027+4 mo
Satvam Hills A6P52100054456JamgaonCertificate Signed30 Jun 202730 Oct 2027+4 mo
Paloma AzureP52100078832MawalCertificate Signed31 Dec 202631 Dec 2026On date
Satvam Hills C5PP1260002601969JamgaonCertificate Signed31 Aug 202931 Aug 2029On date
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology