Company or firm · first RERA registration 2021
Swastivastu Developers Llp
Deedo IDDD-882WOf 4 registrations whose promised date has arrived, 2 kept it (50%). The rest ran a median 13 mo late.
Projects45 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay13 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases1no insolvency
3 registrations of 5 ran past the RERA date
Months late against the original RERA promise, per registration
5 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
| Case | Project | Date |
|---|---|---|
| Quarterly progress report not filed | Nirmiti Residency Wing C And DQuarterly progress report not filed: NIRMITI RESIDENCY WING C AND D | Not on record |
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Nirmiti Residency Wing C And DP53100028586 | Sangli Miraj Kupwad (M Corp.) | Certificate Signed | 2 Aug 2025 | 2 Aug 2025 | On date |
| Nirmiti PrideP53100031034 | Sangli Miraj Kupwad (M Corp.) | Certificate Signed | 9 Sep 2025 | 9 Sep 2025 | +13 mo* |
| Nirmiti PrideP53100031218 | Sangli Miraj Kupwad (M Corp.) | Certificate Signed | 9 Sep 2025 | 9 Sep 2025 | +13 mo* |
| Nirmiti Elite 14P53100031761 | Sangli Miraj Kupwad (M Corp.) | Certificate Signed | 9 Sep 2025 | 9 Sep 2025 | On date |
| Nirmiti Residency Wing EP53100054063 | Sangli Miraj Kupwad (M Corp.) | Certificate Signed | 31 Jul 2027 | 30 Nov 2027 | +4 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology