Skip to content
Company or firm · first RERA registration 2020

Swamini Infra Private Limited

Of 4 registrations whose promised date has arrived, 3 kept it (75%). The rest ran a median 4 mo late.

Projects66 RERA registrations
Kept RERA date75%Maharashtra: 73%
Median delay4 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

3 registrations of 6 ran past the RERA date

Months late against the original RERA promise, per registration

6 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Swarajya-NxP51700027057Badlapur (M Cl)Certificate Signed30 Apr 202430 Apr 2024On date
Silver PrideP51700028369Badlapur (M Cl)Certificate Signed30 Jun 202430 Jun 2024On date
SnehanchalP51700034295AmbarnathCertificate Signed31 Dec 202531 Dec 2025On date
Swami SwarupP51700051631Badlapur (M Cl)Certificate Signed31 May 202631 May 2026+5 mo*
BramhandnayakP51700078848Badlapur (M Cl)Certificate Signed31 Dec 202830 Apr 2029+4 mo
YatigandhPR1330002601085ShirgaonCertificate Signed31 Mar 203131 Jul 2031+4 mo
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology