Company or firm · first RERA registration 2023

Svecha Realty LLP

None of 1 registration has reached its promised completion date yet.

Projects11 RERA registration
Kept RERA dateNone due yet
Median delayNonewhen extended
Completed0as reported on MahaRERA
Regulatory cases0none on record
Svecha Realty LLP developer report cardPDF: every registration against its promise, regulatory matters, professionals and projects by salesSee what's inside · from ₹1,999

No registration has been extended past its RERA date

Months late against the original RERA promise, per registration

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityStatusProposedRevisedDelay
Parshwa Darshan Co Operative Housing Society LimitedP51800052656VileparleCertificate Signed31 Dec 202731 Dec 2027On date