Company or firm · first RERA registration 2019

Suyash Sahakar Builders And Developers

Deedo IDDD-V4WX

Of 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 14 mo late.

Projects22 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay14 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

2 registrations of 2 ran past the RERA date

Months late against the original RERA promise, per registration

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Siddhivinayak ResidencyP52000022815UlaweCertificate Signed30 May 202230 Nov 2022+6 mo
Siddhivinayak Residency IIP52000077666UlaweCertificate Signed31 Dec 202430 Sep 2025+22 mo*
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology