Company or firm · first RERA registration 2017

Suvidha Enterprises

Of 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 4 mo late — the same as Maharashtra's 4 mo.

Projects22 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

1 registration of 2 ran past the RERA date

Months late against the original RERA promise, per registration

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Regal HeightsP99000009178Vasaivirar City (M Corp)Certificate Signed30 Dec 202130 Dec 2021On date
Regal PrideP99000049341VasaiCertificate Signed31 Jul 202630 Nov 2026+4 mo
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology