Individual promoter · first RERA registration 2021

Suresh Namdev Lagad

Of 3 registrations whose promised date has arrived, 1 kept it (33%). The rest ran a median 16 mo late.

Projects33 RERA registrations
Kept RERA date33%Maharashtra: 73%
Median delay16 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

2 registrations of 3 ran past the RERA date

Months late against the original RERA promise, per registration

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Adesh HeightsP52200030368Ahmadnagar (M Corp.)Certificate Signed31 Dec 202331 Dec 2023On date
Adesh Heights Phase 8P52200046099Ahmadnagar (M Corp.)Certificate Signed31 Dec 202431 Dec 2024+22 mo*
Adesh Heights Phase 11P52200051423Ahmadnagar (M Corp.)Certificate Signed31 Dec 202531 Dec 2025+10 mo*
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology