Individual promoter · first RERA registration 2017

Suresh Kashinath Haware

Deedo IDDD-978E

Of 4 registrations whose promised date has arrived, 2 kept it (50%). The rest ran a median 13 mo late.

Projects56 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay13 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

4 registrations of 6 ran past the RERA date

Months late against the original RERA promise, per registration

6 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Haware PinnacleP51700000464MuthavalCertificate Signed30 Sep 202030 Sep 2020On date
Haware ParadiseP51700000844MuthavalCertificate Signed30 Mar 202230 Mar 2022+55 mo*
Haware Intelligentia Sigma South JVLRP51900015562Mumbai CityCertificate Signed30 Dec 202430 Dec 2024+22 mo*
Haware Intelligentia Sigma South JVLR Wing CP51800028288KurlaCertificate Signed31 Dec 202630 Apr 2027+4 mo
Haware Intelligentia Sigma South JVLRP51900028286Mumbai CityCertificate Signed30 Jun 202530 Jun 2025On date
Intelligentia Segment by Haware PropertiesP51700053766Thane (M Corp.)Certificate Signed31 Dec 202730 Apr 2028+4 mo
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology