Skip to content
Company or firm · first RERA registration 2017

Sunrise Lifespaces Llp

Deedo IDDD-2801

Of 2 registrations whose promised date has arrived, 2 kept it (100%).

Projects36 RERA registrations
Kept RERA date100%Maharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

4 registrations of 6 ran past the RERA date

Months late against the original RERA promise, per registration

6 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Sunrise GloryP51700003397Thane (M Corp.)Certificate Signed30 Dec 202230 Dec 2022On date
Sunrise GloryP51700008298Thane (M Corp.)Certificate Signed30 Jun 201830 Jun 2018On date
Sunrise Corporate ParkP51700050406Thane (M Corp.)Certificate Signed31 Dec 202830 Apr 2029+4 mo
Sunrise Corporate ParkP51700079592Thane (M Corp.)Certificate Signed31 Dec 202930 Apr 2030+4 mo
Sunrise Corporate ParkPC1332022501733Thane (M Corp.)Certificate Signed31 Dec 203030 Apr 2031+4 mo
Sunrise CrestviewPR1330002502397Thane (M Corp.)Certificate Signed31 Dec 202930 Apr 2030+4 mo
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology