Company or firm · first RERA registration 2017

Sun-Vision Estates Ltd

Of 3 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 92 mo late.

Projects33 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay92 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

3 registrations of 3 ran past the RERA date

Months late against the original RERA promise, per registration

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Swarup NiketanP51800001497AndheriCertificate Signed28 Feb 201927 Feb 2020+92 mo*
Paresh KunjP51800001747AndheriCertificate Signed30 Apr 201930 Jun 2022+90 mo*
Jai ShubamkarotiP51800002366AndheriCertificate Signed31 Dec 201731 Dec 2017+106 mo*
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology