Company or firm · first RERA registration 2020
Sumer Corporation
Of 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 39 mo late — longer than Maharashtra's 4 mo.
Projects22 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay39 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases2no insolvency
2 registrations of 2 ran past the RERA date
Months late against the original RERA promise, per registration
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
| Case | Project | Date |
|---|---|---|
| Regulatory order | Sumer LifeRegulatory order: PROJECT NAME: SUMER LIFE (Regulatory Case No. 390 OF 2025) dated 17 July, 2025. | 17 Jul 2025 |
| Regulatory order | Sumer Life CasaRegulatory order: PROJECT NAME: SUMER LIFE CASA (Regulatory Case No. 388 OF 2025) dated 17 July, 2025. | 17 Jul 2025 |
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Sumer LifeP51800024414 | Kurla | Certificate Signed | 30 Dec 2024 | 31 Dec 2027 | +36 mo |
| Sumer Life CasaP51800026539 | Kurla | Certificate Signed | 30 Jun 2024 | 31 Dec 2027 | +42 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology