Sumer Corporation

Of 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 39 mo late — longer than Maharashtra's 4 mo.

Projects22 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay39 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases2no insolvency

2 registrations of 2 ran past the RERA date

Months late against the original RERA promise, per registration

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Sumer LifeP51800024414KurlaCertificate Signed30 Dec 202431 Dec 2027+36 mo
Sumer Life CasaP51800026539KurlaCertificate Signed30 Jun 202431 Dec 2027+42 mo
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology