Sujeet Kumar Singh

Deedo IDDD-9B3M

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 8 mo late.

Projects22 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay8 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

2 registrations of 2 ran past the RERA date

Months late against the original RERA promise, per registration

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Padamavati Royal Phase 1P51700023535TitwalaCertificate Signed28 Nov 202528 Nov 2025+11 mo*
Padamavati Royal Phase 2P51700023536TitwalaCertificate Signed31 Dec 202930 Apr 2030+4 mo
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology