Company or firm · first RERA registration 2017

Strawberry Constructions Pvt. Ltd

Of 5 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 33 mo late.

Projects78 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay33 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

8 registrations of 8 ran past the RERA date

Months late against the original RERA promise, per registration

8 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
OnyxP51700004512Mirabhayandar (M Corp.)Certificate Signed30 Jun 201929 Dec 2020+18 mo
The AddressP51700010224Mirabhayandar (M Corp.)Certificate Signed30 Jun 20217 Mar 2024+64 mo*
The AddressP51700010395Mirabhayandar (M Corp.)Certificate Signed30 Dec 202231 Dec 2028+72 mo
The Address Bldg. No. 1P51700018632ThaneCertificate Signed30 Dec 202331 Dec 2028+60 mo
The Address Bldg. No. 6P51700018682ThaneCertificate Signed30 Dec 202331 Dec 2027+48 mo
The Address Building No.4P51700029361Mirabhayandar (M Corp.)Certificate Signed31 Dec 202630 Apr 2027+4 mo
The Address Building No. 3P51700029362ThaneCertificate Signed31 Dec 202630 Apr 2027+4 mo
The Address Building No. 2P51700029653ThaneCertificate Signed31 Dec 202630 Apr 2027+4 mo
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology