Company or firm · first RERA registration 2017
Srujan Development And Construction Division
Of 1 registration whose promised date has arrived, 0 were never extended past it (0%). When extended, the date moved a median 42 mo — longer than Maharashtra's 4 mo.
Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay42 mowhen extended · Maharashtra: 4 mo
Completed0as reported on MahaRERA
Regulatory cases1no insolvency
1 registration of 1 moved past the RERA date
Months late against the original RERA promise, per registration
1 registration with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
| Case | Project | Date |
|---|---|---|
| Regulatory order | VedaRegulatory order: PROJECT NAME: VEDA (Regulatory Case No.79 of 2023) dated 22 November 2023. | 25 Nov 2023 |
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| VedaP51800002383 | Andheri | Certificate Signed | 30 Jun 2021 | 31 Dec 2024 | +42 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology