Sree Padmanabhan Nair

Of 3 registrations whose promised date has arrived, 1 kept it (33%). The rest ran a median 60 mo late.

Projects33 RERA registrations
Kept RERA date33%Maharashtra: 73%
Median delay60 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

2 registrations of 3 ran past the RERA date

Months late against the original RERA promise, per registration

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Siddhesh ApartmentP52000006645BokadviraCertificate Signed31 Jul 201831 Jul 2019+99 mo*
Shree Laxmi ApartmentsP52000007759BokadviraCertificate Signed31 Dec 201731 Dec 2017On date
Riddhesh ApartmentsP52000020336BokadviraCertificate Signed28 Feb 202528 Feb 2025+20 mo*
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology