Skytech Infra

Company or firm · 4 projects · 4 MahaRERA registrations

4Projects4 RERA registrations
0Completedas reported on MahaRERA project pages
75%Kept RERA date3 of 4 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Neelkanth GreenP52000018387Kamothe2018Certificate Signed30 Dec 202330 Dec 2023On date
Neelkanth ClassicP52000021980Kharghar2019Certificate Signed30 Dec 202330 Dec 2023On date
Neelkanth DarshanP52000034879Kamothe2022Certificate Signed31 Dec 202431 Dec 2024On date
Neelkanth AvenueP52000047513Kharghar2022Certificate Signed30 Jun 202630 Oct 2026+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Neelkanth GreenOn date
  • Neelkanth ClassicOn date
  • Neelkanth DarshanOn date
  • Neelkanth Avenue+4 mo

Track record notes

  • 3 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 4 months, for Neelkanth Avenue (P52000047513).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology