Skyrise Ventures Llp

Of 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 10 mo late.

Projects12 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay10 mowhen late
Flats sold, all time53registered sale deeds
Regulatory cases0none on record

2 registrations of 2 ran past the RERA date

Months late against the original RERA promise, per registration

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
SparkleP52100032572DhanoriCertificate Signed30 Jun 202530 Jun 2025+16 mo*
SparkleP52100055140DhanoriCertificate Signed30 Jun 202630 Oct 2026+4 mo
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology