Company or firm · first RERA registration 2018

Skyblue Homes Private Limited

Deedo IDDD-1K7D

Of 3 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 39 mo late.

Projects33 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay39 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

3 registrations of 3 ran past the RERA date

Months late against the original RERA promise, per registration

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Pleasure GardenP52800018654Dapoli CampCertificate Signed30 Dec 202330 Dec 2023+34 mo*
Chougley HeritageP52800027412Dapoli CampCertificate Signed30 Jul 202330 Jul 2023+39 mo*
Abdul Aziz ApartmentP52800028395Dapoli CampCertificate Signed30 Jun 202230 Jun 2022+52 mo*
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology