Sky Developers
Deedo IDDD-2VDQOf 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 16 mo late.
Delivery record
1 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| White ArkP52000020245 | Ulawe | Certificate Signed | 30 Dec 2021 | 30 Dec 2021 | On date |
| Sky SignatureP51700052954 | Navi Mumbai (M Corp.) | Certificate Signed | 5 Jun 2025 | 5 Jun 2025 | +16 mo* |
Sky Developers, in questions
Does Sky Developers finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 1 kept it (50%). The rest ran a median 16 mo late. Across Maharashtra, 73% kept their date.
How many projects has Sky Developers registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 1 completed on MahaRERA.
Does Sky Developers have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.