Sita Sadashiv Patil

Deedo IDDD-F1RY

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 36 mo late.

Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay36 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases1no insolvency

Delivery record

1 of 1 registration with dates moved or missed their RERA date · months late against the original promise

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Ms Machindranath EnterprisesP51700029331KalyanCertificate Signed1 Oct 20231 Oct 2023+36 mo*

Sita Sadashiv Patil, in questions

Does Sita Sadashiv Patil finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 36 mo late. Across Maharashtra, 73% kept their date.

How many projects has Sita Sadashiv Patil registered with MahaRERA?

1 project under 1 MahaRERA registration; 0 completed on MahaRERA.

Does Sita Sadashiv Patil have MahaRERA regulatory cases?

1 regulatory case name its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology