Company or firm · first RERA registration 2017
Simran Enterprises
Of 5 registrations whose promised date has arrived, 4 were never extended past it (80%).
Projects45 RERA registrations
Kept RERA date80%
Median delayNonewhen extended
Completed0as reported on MahaRERA
Regulatory cases0none on record
1 registration of 5 moved past the RERA date
Months late against the original RERA promise, per registration
5 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Building No. 2, Uptown AvenueP51900001068 | Panvel | Certificate Signed | 31 Dec 2017 | 30 Jun 2018 | +6 mo |
| Building no. 1 , Uptown AvenueP52000016037 | Panvel | Certificate Signed | 30 Dec 2022 | 30 Dec 2022 | On date |
| Sakasi GreensP52000023509 | Akurli | Certificate Signed | 30 Dec 2023 | 30 Dec 2023 | On date |
| Building no. 1 , Uptown AvenueP52000024151 | Panvel | Certificate Signed | 30 Dec 2024 | 30 Dec 2024 | On date |
| Jindal ParkP52000047020 | Akurli | Certificate Signed | 31 Mar 2025 | 31 Mar 2025 | On date |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology