Silver Star Group
Deedo IDDD-CD65Of 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 10 mo late.
Projects44 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay10 mowhen late
Flats sold, all time35registered sale deeds
Regulatory cases0none on record
2 registrations of 4 ran past the RERA date
Months late against the original RERA promise, per registration
4 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Silver Palm Grove Phase 2P52100008351 | Pimpri Chinchawad (M Corp.) | Certificate Signed | 30 Dec 2019 | 30 Dec 2019 | On date |
| The Silver Altair Tower-CP52100035075 | Ravet | Certificate Signed | 31 Mar 2027 | 31 Jul 2027 | +4 mo |
| The Silver Altair Tower-D MhadaP52100049673 | Ravet | Certificate Signed | 28 Jul 2025 | 28 Jul 2025 | +15 mo* |
| The Silver AltairP52100080295 | Ravet | Certificate Signed | 31 Dec 2028 | 31 Dec 2028 | On date |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology