Company or firm · first RERA registration 2021

Silver Oak Builders And Developers

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 13 mo late.

Projects22 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay13 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

2 registrations of 2 ran past the RERA date

Months late against the original RERA promise, per registration

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Silveroak Gold CoastP52200028247Shirdi(N P)Certificate Signed23 Dec 202423 Dec 2025+22 mo*
Shriyans 3.0P52100054165PunawaleCertificate Signed31 Oct 202729 Feb 2028+4 mo
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology