Company or firm · first RERA registration 2017

Siddhivinayak Namrata Developers

Of 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 36 mo late — longer than Maharashtra's 4 mo.

Projects22 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay36 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

1 registration of 2 ran past the RERA date

Months late against the original RERA promise, per registration

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Vision FloraP52100009594Pimpale SaudagarCertificate Signed31 Dec 201830 Dec 2021+36 mo
Vision FloraP52100029188Pimpale SaudagarCertificate Signed30 Apr 202630 Apr 2026On date
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology