Siddhivinayak Infrastructure
Deedo IDDD-2P5TOf 2 registrations whose promised date has arrived, 2 kept it (100%).
Delivery record
None of 2 registrations with dates has moved or missed its RERA date
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Shiv-Govind JasmineP50500046421 | Nagpur (M Corp.) | Certificate Signed | 31 Dec 2024 | 31 Dec 2024 | On date |
| Shiv-Govind LotusP50500076954 | Nagpur (M Corp.) | Certificate Signed | 31 Mar 2026 | 31 Mar 2026 | On date |
Siddhivinayak Infrastructure, in questions
Does Siddhivinayak Infrastructure finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 2 kept it (100%). Across Maharashtra, 73% kept their date.
How many projects has Siddhivinayak Infrastructure registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 2 completed on MahaRERA.
Does Siddhivinayak Infrastructure have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.