Company or firm · first RERA registration 2017
Siddhivinayak Developers
Of 1 registration whose promised date has arrived, 1 kept it (100%).
Projects22 RERA registrations
Kept RERA date100%Maharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record
1 registration of 2 ran past the RERA date
Months late against the original RERA promise, per registration
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Shubham Shanti ResidencyP52900012484 | Kudal (Ct) | Certificate Signed | 30 Sep 2019 | 30 Sep 2019 | On date |
| Siddhivinayak DevelopersP52900028637 | Kudal (Ct) | Certificate Signed | 25 Aug 2027 | 25 Dec 2027 | +4 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology