Sidaan Enterprise

Deedo IDDD-H8QT

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 17 mo late — longer than Maharashtra's 4 mo.

Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay17 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

Delivery record

1 of 1 registration with dates moved or missed their RERA date · months late against the original promise

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Sadhanaa BuildingP51900023932Mumbai CityCertificate Signed30 May 202218 Oct 2023+17 mo

Sidaan Enterprise, in questions

Does Sidaan Enterprise finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 17 mo late. Across Maharashtra, 73% kept their date.

How many projects has Sidaan Enterprise registered with MahaRERA?

1 project under 1 MahaRERA registration; 1 completed on MahaRERA.

Does Sidaan Enterprise have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology