Company or firm · first RERA registration 2019
Shubh Infratech
Of 3 registrations whose promised date has arrived, 1 kept it (33%). The rest ran a median 26 mo late.
Projects33 RERA registrations
Kept RERA date33%Maharashtra: 73%
Median delay26 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record
2 registrations of 3 ran past the RERA date
Months late against the original RERA promise, per registration
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Kanchan Nagri-5P50500022544 | Takli | Certificate Signed | 30 Dec 2021 | 31 Dec 2023 | +24 mo |
| Kanchan Nagri-3P50500026187 | Mondha | Certificate Signed | 30 Jun 2024 | 30 Jun 2024 | +28 mo* |
| Kanchan Nagari 8P50500045693 | Wanadongri (Ct) | Certificate Signed | 31 Dec 2025 | 31 Dec 2025 | On date |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology