Company or firm · first RERA registration 2017

Shri Siddhivinayak Developers

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 7 mo late — longer than Maharashtra's 4 mo.

Projects12 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay7 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

2 registrations of 2 ran past the RERA date

Months late against the original RERA promise, per registration

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Ganga AmberP52100002620TathwadeCertificate Signed30 Jun 202230 Apr 2023+10 mo
Ganga AmberP52100026055TathwadeCertificate Signed30 Jun 202730 Oct 2027+4 mo
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology