Company or firm · first RERA registration 2022
Shri Samarth Construction
Of 1 registration whose promised date has arrived, 1 kept it (100%).
Projects33 RERA registrations
Kept RERA date100%Maharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record
1 registration of 3 ran past the RERA date
Months late against the original RERA promise, per registration
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Harikrupa residencyP52600033486 | Wakhari | Certificate Signed | 31 Dec 2025 | 31 Dec 2025 | On date |
| Harikrupa HeightsP52600050906 | Wakhari | Certificate Signed | 31 Dec 2026 | 31 Dec 2026 | On date |
| Shantais ParadiseP52600080531 | Isbavi | Certificate Signed | 31 Dec 2027 | 30 Apr 2028 | +4 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology