Shri Sairaj Associates

Of 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 24 mo late — longer than Maharashtra's 4 mo.

Projects22 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay24 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

1 registration of 2 ran past the RERA date

Months late against the original RERA promise, per registration

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
K52 Building AP52100019093Pune (M Corp.)Certificate Signed30 Oct 202130 Oct 2021On date
KBC Tower Karvenagar Business ComplexP52100030700Karve NagarCertificate Signed28 Feb 202328 Feb 2025+24 mo
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology