Skip to content
Company or firm · first RERA registration 2020

Shri Balaji Sudarshan

Of 1 registration whose promised date has arrived, 1 were never extended past it (100%).

Projects22 RERA registrations
Kept RERA date100%
Median delayNonewhen extended
Completed0as reported on MahaRERA
Regulatory cases2no insolvency
Shri Balaji Sudarshan developer report cardPDF: every registration against its promise, regulatory matters, professionals and projects by salesSee what's inside · from ₹1,999

No registration has been extended past its RERA date

Months late against the original RERA promise, per registration

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityStatusProposedRevisedDelay
Balaji SudarshanP52100026156HaveliCertificate Signed1 Jun 20251 Jun 2025On date
Shri Balaji SudarshanP52100050258Pune (M Corp.)Certificate Signed1 Dec 20261 Dec 2026On date