Company or firm · first RERA registration 2019

Shri Ashtavinayak Enterprises

Of 2 registrations whose promised date has arrived, 2 were never extended past it (100%).

Projects55 RERA registrations
Kept RERA date100%
Median delayNonewhen extended
Completed0as reported on MahaRERA
Regulatory cases0none on record
Shri Ashtavinayak Enterprises developer report cardPDF: every registration against its promise, regulatory matters, professionals and projects by salesSee what's inside · from ₹1,999

2 registrations of 5 moved past the RERA date

Months late against the original RERA promise, per registration

5 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityStatusProposedRevisedDelay
Vinayak AvenueP52000020466KaranjadeCertificate Signed30 Dec 202230 Dec 2022On date
Vinayak AtithiP52000022347KaranjadeCertificate Signed30 Dec 202330 Dec 2023On date
Vinayak ChhayaP52000050503Taloje PanchnadCertificate Signed31 Dec 202630 Apr 2027+4 mo
Vinayak ShradhaP52000056448KaranjadeCertificate Signed31 Dec 202731 Dec 2027On date
Vinayak VistaP52000078701Taloje PanchnadCertificate Signed31 Dec 203030 Apr 2031+4 mo
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology