Company or firm · first RERA registration 2017

Shreeram Builders

Of 5 registrations whose promised date has arrived, 5 kept it (100%).

Projects66 RERA registrations
Kept RERA date100%Maharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

1 registration of 6 ran past the RERA date

Months late against the original RERA promise, per registration

6 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Sumeet Co-operative Housing SocietyP52100009620ParvatiCertificate Signed31 Dec 201731 Dec 2017On date
Yashwant ApartmentP52100011553ParvatiCertificate Signed31 Dec 201731 Dec 2017On date
Ramalay ApartmentP52100017117ParvatiCertificate Signed30 Jun 202230 Jun 2022On date
Gulmohar ApartmentP52100017155ParvatiCertificate Signed30 Oct 202130 Oct 2021On date
Vithal NiwasP52100024779Pune CityCertificate Signed30 May 202330 May 2023On date
Shree Ram PlazaP52100048761Pune (M Corp.)Certificate Signed15 Dec 202615 Apr 2027+4 mo
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology