Company or firm · first RERA registration 2024

Shreepati Group

Deedo IDDD-P95E

None of 2 registrations has reached its promised completion date yet.

Projects22 RERA registrations
Kept RERA dateNone due yetMaharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

1 registration of 2 ran past the RERA date

Months late against the original RERA promise, per registration

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Shreepati RegaliaP52000056403PushapakCertificate Signed31 Dec 202630 Apr 2027+4 mo
Shreepati SukhkartaPR1270002602041Pushpak NagarCertificate Signed31 Dec 203131 Dec 2031On date
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology