Company or firm · first RERA registration 2017

Shreedham Construction Private Limited

Deedo IDDD-J2S3

Of 3 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 34 mo late.

Projects33 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay34 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases3includes insolvency

3 registrations of 3 ran past the RERA date

Months late against the original RERA promise, per registration

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

CaseProjectDate
Listed as an NCLT insolvency projectShreedham ClassicListed as NCLT project: Shreedham ClassicNot on record
Listed as an NCLT insolvency projectShreedham ExcellencyListed as NCLT project: Shreedham ExcellencyNot on record
Listed as an NCLT insolvency projectCrystal HomesListed as NCLT project: Crystal HomesNot on record

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Crystal HomesP51700007282NhaveCertificate Signed30 Dec 202330 Dec 2023+34 mo*
Shreedham ExcellencyP51700012299Mirabhayandar (M Corp.)Certificate Signed30 Dec 202230 Dec 2022+46 mo*
Shreedham ClassicP51800012234AndheriCertificate Signed31 Dec 201831 Dec 2019+12 mo
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology