Skip to content
Company or firm · first RERA registration 2019

Shree Swami Samarth Developers

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 55 mo late.

Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay55 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

1 registration of 1 ran past the RERA date

Months late against the original RERA promise, per registration

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Ariana ImperialP52100019772WakadCertificate Signed30 Mar 202230 Mar 2022+55 mo*
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology