Company or firm · first RERA registration 2017
Shree Squarefeet Enterprises Llp
Of 3 registrations whose promised date has arrived, 3 were never extended past it (100%).
Projects13 RERA registrations
Kept RERA date100%Maharashtra: 73%
Median delayNonewhen extended · Maharashtra: 4 mo
Completed0as reported on MahaRERA
Regulatory cases0none on record
No registration has been extended past its RERA date
Months late against the original RERA promise, per registration
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Sarvoday SquareP51700010034 | Ambarnath(M Cl) | Certificate Signed | 1 Dec 2021 | 1 Dec 2021 | On date |
| Sarvoday SquareP51700018388 | Ambarnath(M Cl) | Certificate Signed | 30 Dec 2025 | 30 Dec 2025 | On date |
| Sarvoday SquareP51700027546 | Ambarnath(M Cl) | Certificate Signed | 30 Jun 2026 | 30 Jun 2026 | On date |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology