Shree Siddhi Construction

Deedo IDDD-AQDQ

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 64 mo late.

Projects22 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay64 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

1 registration of 2 ran past the RERA date

Months late against the original RERA promise, per registration

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Rajeshwari ResidencyP51700005861MandaCertificate Signed30 Jun 202120 Jun 2022+64 mo*
Rajeshwari Residency Phase IIP51700025220Kalyan-Dombivali (M Corp.)Certificate Signed31 Dec 202731 Dec 2027On date
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology