Company or firm · first RERA registration 2019
Shree Samarthkrupa Builders & Developers
Of 1 registration whose promised date has arrived, 1 were never extended past it (100%).
Projects22 RERA registrations
Kept RERA date100%
Median delayNonewhen extended
Completed0as reported on MahaRERA
Regulatory cases0none on record
1 registration of 2 moved past the RERA date
Months late against the original RERA promise, per registration
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Samarth SarthiP52800022301 | Jalgaon | Certificate Signed | 30 Oct 2022 | 30 Oct 2022 | On date |
| Samarth OrchidP52800025686 | Dapoli Camp | Certificate Signed | 31 Dec 2026 | 30 Apr 2027 | +4 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology