Company or firm · first RERA registration 2017
Shree Sai Datta Developers
Deedo IDDD-DHNQOf 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 55 mo late.
Projects22 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay55 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record
2 registrations of 2 ran past the RERA date
Months late against the original RERA promise, per registration
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Govind NiwasP51900012407 | Mumbai City | Certificate Signed | 14 Dec 2020 | 30 Apr 2023 | +70 mo* |
| Yashraj PristineP51900021418 | Ward Fnorth | Certificate Signed | 30 Jun 2023 | 31 Dec 2025 | +40 mo* |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology
