Company or firm · first RERA registration 2021
Shree Sai Buildcon
Of 1 registration whose promised date has arrived, 1 were never extended past it (100%).
Projects22 RERA registrations
Kept RERA date100%
Median delayNonewhen extended
Completed0as reported on MahaRERA
Regulatory cases0none on record
1 registration of 2 moved past the RERA date
Months late against the original RERA promise, per registration
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Shree Sai ValleyP51600032264 | Nashik (M Corp.) | Certificate Signed | 20 Jan 2024 | 20 Jan 2024 | On date |
| Shree Sai PalaceP51600078798 | Nashik | Certificate Signed | 31 Dec 2027 | 30 Apr 2028 | +4 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology