Company or firm · first RERA registration 2017

Shree Radhakrishna Developer

Of 2 registrations whose promised date has arrived, 1 were never extended past it (50%). When extended, the date moved a median 2 mo — shorter than Maharashtra's 4 mo.

Projects12 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay2 mowhen extended · Maharashtra: 4 mo
Completed0as reported on MahaRERA
Regulatory cases0none on record
Shree Radhakrishna Developer developer report cardPDF: every registration against its promise, regulatory matters, professionals and projects by salesSee what's inside · from ₹1,999

1 registration of 2 moved past the RERA date

Months late against the original RERA promise, per registration

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityStatusProposedRevisedDelay
SiliconP51700004184Badlapur (M Cl)Certificate Signed31 May 201831 May 2018On date
SiliconP51700019695Badlapur (M Cl)Certificate Signed30 Dec 202121 Feb 2022+2 mo
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology