Company or firm · first RERA registration 2017
Shree Radhakrishna Developer
Of 2 registrations whose promised date has arrived, 1 were never extended past it (50%). When extended, the date moved a median 2 mo — shorter than Maharashtra's 4 mo.
Projects12 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay2 mowhen extended · Maharashtra: 4 mo
Completed0as reported on MahaRERA
Regulatory cases0none on record
1 registration of 2 moved past the RERA date
Months late against the original RERA promise, per registration
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| SiliconP51700004184 | Badlapur (M Cl) | Certificate Signed | 31 May 2018 | 31 May 2018 | On date |
| SiliconP51700019695 | Badlapur (M Cl) | Certificate Signed | 30 Dec 2021 | 21 Feb 2022 | +2 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology