Shree Prabha Construction
Deedo IDDD-3ZEMOf 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 5 mo late.
Delivery record
3 of 3 registrations with dates moved or missed their RERA date · months late against the original promise
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Shree Mauli PrabhaP51700029414 | Dombivli | Certificate Signed | 31 Jul 2024 | 31 Oct 2024 | +28 mo* |
| Shreerang KutirP51700052997 | Kalyandombivali (M Corp.) | Certificate Signed | 1 Jun 2026 | 1 Oct 2026 | +5 mo* |
| Shree DeepjyotiPR1330002500684 | Dombivli | Certificate Signed | 31 Mar 2029 | 31 Jul 2029 | +4 mo |
Shree Prabha Construction, in questions
Does Shree Prabha Construction finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 5 mo late. Across Maharashtra, 73% kept their date.
How many projects has Shree Prabha Construction registered with MahaRERA?
3 projects under 3 MahaRERA registrations; 0 completed on MahaRERA.
Does Shree Prabha Construction have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.