Company or firm · first RERA registration 2018

Shree Mangalmurti Associates Phase-I

Of 1 registration whose promised date has arrived, 0 were never extended past it (0%). When extended, the date moved a median 53 mo — longer than Maharashtra's 4 mo.

Projects12 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay53 mowhen extended · Maharashtra: 4 mo
Completed0as reported on MahaRERA
Regulatory cases0none on record
Shree Mangalmurti Associates Phase-I developer report cardPDF: every registration against its promise, regulatory matters, professionals and projects by salesSee what's inside · from ₹1,999

1 registration of 2 moved past the RERA date

Months late against the original RERA promise, per registration

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityStatusProposedRevisedDelay
Green FantasyP52100016541Uruli KanchanCertificate Signed31 Dec 202731 Dec 2027On date
Green FantasyP52100016595Uruli KanchanCertificate Signed30 Apr 201930 Sep 2023+53 mo
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology