Company or firm · first RERA registration 2017
Shree Mahavir Properties
Of 1 registration whose promised date has arrived, 0 were never extended past it (0%).
Projects22 RERA registrations
Kept RERA date0%
Median delayNonewhen extended
Completed0as reported on MahaRERA
Regulatory cases0none on record
2 registrations of 2 moved past the RERA date
Months late against the original RERA promise, per registration
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Redevelopment of Juhu Shantivan CHSLP51800001772 | Mumbai | Certificate Signed | 31 Mar 2019 | 30 Sep 2020 | +18 mo |
| Delite DenP51800080552 | Juhu | Certificate Signed | 31 Dec 2030 | 30 Apr 2031 | +4 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology