Company or firm · first RERA registration 2018
Shree Ganesh Builders & Developers
Of 1 registration whose promised date has arrived, 1 were never extended past it (100%).
Projects22 RERA registrations
Kept RERA date100%
Median delayNonewhen extended
Completed0as reported on MahaRERA
Regulatory cases0none on record
No registration has been extended past its RERA date
Months late against the original RERA promise, per registration
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Shree Gauri KrupaP52000018981 | Navi Mumbai Panvel Rigardh (Ct) | Certificate Signed | 30 Dec 2021 | 30 Dec 2021 | On date |
| Maitri ResidencyP52000054260 | Navade | Certificate Signed | 31 Dec 2026 | 31 Dec 2026 | On date |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology