Company or firm · first RERA registration 2017
Shree Construction
Of 1 registration whose promised date has arrived, 0 were never extended past it (0%).
Projects33 RERA registrations
Kept RERA date0%
Median delayNonewhen extended
Completed0as reported on MahaRERA
Regulatory cases0none on record
2 registrations of 3 moved past the RERA date
Months late against the original RERA promise, per registration
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Shree Township Building - 5, Type-A, Being No.11P99000013415 | Kambalgaon | Certificate Signed | 31 Oct 2019 | 30 Oct 2021 | +24 mo |
| Sharda HeightP99000028119 | Vasai Virar City (M Corp) | Certificate Signed | 30 Jun 2028 | 30 Jun 2028 | On date |
| Laxmi TowerP99000045857 | Vasaivirar City (M Corp) | Certificate Signed | 31 Dec 2030 | 30 Apr 2031 | +4 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology