Skip to content
Company or firm · first RERA registration 2017

Shree Construction

Of 1 registration whose promised date has arrived, 0 were never extended past it (0%).

Projects33 RERA registrations
Kept RERA date0%
Median delayNonewhen extended
Completed0as reported on MahaRERA
Regulatory cases0none on record
Shree Construction developer report cardPDF: every registration against its promise, regulatory matters, professionals and projects by salesSee what's inside · from ₹1,999

2 registrations of 3 moved past the RERA date

Months late against the original RERA promise, per registration

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityStatusProposedRevisedDelay
Shree Township Building - 5, Type-A, Being No.11P99000013415KambalgaonCertificate Signed31 Oct 201930 Oct 2021+24 mo
Sharda HeightP99000028119Vasai Virar City (M Corp)Certificate Signed30 Jun 202830 Jun 2028On date
Laxmi TowerP99000045857Vasaivirar City (M Corp)Certificate Signed31 Dec 203030 Apr 2031+4 mo
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology